Three Phases of Preparations for the Beijing Olympic Games
Preparations can be divided into 3 phases from January 2002 to 2008:

1) Preparatory Phase (2002 - June 2003): The proposal for Olympic Movement will be drafted and implemented to strengthen the organizational leadership structure. Funding and preparations for stadium construction will be proposed and agreed. Implementation of projects for environmental protection and fundamental facilities will be accelerated.

2) Overall Construction Phase (2003 July - 2006): All stadium construction will be initiated, and as completed, some stadiums will be in use prior to the deadline. By the end of 2006, all construction will be completed.

3) Testing and Adjustment Phase (2007 - 2008): All construction will be tested, adjustments made and practices and trials undertaken, to ensure all facilities and services meet the demands for holding the Olympic Games.